The 100-year-old pond loses more than 30,000 gallons a week; a $5 million redesign would deepen it to protect the koi, with work set to start in November 2027.

Knox Abbott

October 3, 20262 min read

Garden koi pond and bridge - illustration, Jake Team LLC

The koi pond at Hakone Gardens, an original feature of the Japanese garden that is more than a century old, is leaking upward of 30,000 gallons a week, and Saratoga's Public Works Department is asking the City Council to put $2.5 million toward rebuilding it.

The request is on the consent calendar for the council's Wednesday, Oct. 7, meeting, meaning it could be approved with other routine items in a single vote unless a council member or resident asks to pull it for discussion.

The staff report by Public Works Director John Cherbone puts the full renovation at about $5 million, with the other half to come from private donors and the Hakone Foundation.

What the work would fix

Cracks in the pond's lining account for the water loss, according to the report. The pond is only about a foot and a half deep, which lets the water heat up quickly in hot weather and raises the risk of disease for the fish.

The redesign would take it to roughly 3.5 feet, giving the koi cooler water and somewhere to retreat from herons, raccoons and other predators. The edges would also be reshaped to discourage those animals.

New bottom drains, skimmers and aerators would improve circulation in parts of the pond that now get too little oxygen. They would tie into the pump house rebuilt in 2019 for about $600,000, which was designed with a deeper pond in mind.

The paths around the water would be regraded and partly rerouted along the hillside so visitors with limited mobility can circle the pond and so the walkways meet accessibility rules.

Designer and schedule

The plans are about 75% done and are being drawn by Hoichi Kurisu, a Japanese garden designer the report credits with more than 2,500 gardens over a 66-year career. The project is the first phase of the Hakone Gardens Master Plan completed in 2016 by the city, the Hakone Foundation and residents.

Because the garden is open year-round and books weddings and events a year out, the city is scheduling well ahead: bidding by Aug. 1, 2027, construction starting Nov. 1, 2027, and completion targeted for June 2028.

The money would come from the city's Park Development Fund, which has about $4.23 million unallocated; the appropriation would leave about $1.73 million. The pond was among a second tier of park projects the council approved for funding this fiscal year if enough park development fees came in.

The council's regular session begins at 7 p.m. at the Saratoga Civic Theater, 13777 Fruitvale Ave., and is also available on Zoom.

Sources

saratoga.ca.us

saratoga.granicus.com

Share

Knox Abbott

Knox Abbott covers Saratoga city hall, the council, and county government.

Related Stories

More in California