Stevens Creek Quarry, without a use permit since 2016, gets its yearly county review Thursday

County planners say the Stevens Canyon Road quarry met its conditions in 2025, while a new permit stalls over land inside Cupertino's city limits and a $10.6 million cleanup bond stays on file.

Sasha Lowery· AI-assisted, edited by Jake Team

November 15, 20262 min read

planning site review - illustration, Jake Team LLC

Santa Clara County planning commissioners on Thursday take their yearly look at Stevens Creek Quarry, the mining and recycling operation on Stevens Canyon Road outside Cupertino that has been running without a current use permit for nearly a decade.

The county's Department of Planning and Development reports that the quarry complied with its conditions of approval during 2025. Inspectors visited 10 times last year, monthly in most months plus an annual state mining inspection in August and a winterization check in December.

The conditions they tracked include sweeping Stevens Canyon Road and suppressing dust, staying within the county noise ordinance, keeping up signs and fencing, and patrolling truck speeds on the haul route.

A permit that lapsed in 2016

The use permit for the quarry's southern parcel, where the entrance, scale house and recycling and composting operations sit, was a 20-year permit. The owner applied to renew it in December 2014, but the Planning Commission continued the hearing in May 2015 at the county's request and never rescheduled it, so the permit expired.

The quarry has operated since under a 2018 compliance agreement with the county, which lets it keep running as long as it meets set milestones toward a new permit and an amended reclamation plan.

That application was filed in September 2020 and deemed complete in December 2021. An environmental impact report is being prepared, but the county report says the work stalled while staff and the operator sorted out a complication: part of the mining operation lies on parcels under the City of Cupertino's jurisdiction.

The operator first planned to have those areas detached and is now weighing other options. The county has agreed to push back the compliance deadlines and is working on new ones.

A 2021 county notice of violation over unpermitted structures led to a 2022 compliance agreement. Several buildings were later declared unsafe, and the report says the operator has since torn down the rock crusher structure, the lower scale house, all 11 office trailers and other structures. An amended agreement signed Oct. 29, 2025, lists what remains to be fixed.

Water quality and a $10.6 million bond

Regional water regulators told the county the quarry exceeded its monthly limit for chromium (VI) in discharge water in January and February 2025. The San Francisco Bay Regional Water Quality Control Board took no further enforcement action because the quarry was meeting its cease-and-desist order, and the quarry has since installed treatment to remove chromium (VI).

Regulators plan to reissue its discharge permit and lift that order by June 30, 2027.

The county also holds a $10,600,371 bond, matching the operator's latest estimate of what it would cost to reclaim the site, which can be used if needed to restore the land.

The commission meets at 6 p.m. Thursday, Nov. 19. The item is listed for acceptance of the annual report, not a permit decision.

Sources

sccgov.iqm2.com

sccgov.iqm2.com

Share

Sasha Lowery· AI-assisted, edited by Jake Team

Sasha Lowery writes about community life, schools, public safety, and local events in Saratoga.

Related Stories

More in California