Valley Water finishes the $176 million Upper Llagas Creek flood project, decades after it was first promised

Officials cut the ribbon Monday on 13.9 miles of channel work in Morgan Hill, Gilroy and San Martin, paid for in part by the countywide Safe, Clean Water measure and an $80 million federal grant.

Sasha Lowery· AI-assisted, edited by Jake Team

November 18, 20262 min read

Creek flood infrastructure - illustration, Jake Team LLC

A South County flood project that Valley Water first pledged to build in 1954 is done, in time for a winter forecasters expect to be shaped by El Niño.

Officials from every level of government cut the ribbon Monday, Nov. 16, on the Upper Llagas Creek project, the Morgan Hill Times reported. The $176.2 million effort spans 13.9 miles of work along Llagas Creek and its West and East Little Llagas branches, running through Morgan Hill, Gilroy and the unincorporated community of San Martin.

According to Valley Water, roughly 1,100 homes and 500 businesses, along with upward of 1,300 acres of farmland, now have protection from a 100-year flood.

How it was paid for

The project started as a U.S. Army Corps of Engineers effort that stalled for years without money. About 10 years ago Valley Water picked it up and chose local funding, the agency's board chair, Tony Estremera, told the crowd, according to the Times. He thanked the voters behind Valley Water's Safe, Clean Water and Natural Flood Protection Program, a countywide measure.

Rep. Zoe Lofgren said she worked to land $80 million from the federal Natural Resources Conservation Service in 2024 to cover the shortfall. Morgan Hill and the state's water resources department also put money in.

What was built

The final phase, under way since October 2024, widened and deepened about eight miles of channel between Highway 101 and Llagas Road, improved crossings and added underground culverts. Earlier phases added a tunnel of about 2,300 feet beneath downtown Morgan Hill and new wetland habitat at Lake Silveira.

Morgan Hill officials have said the project should take some neighborhoods off FEMA flood maps, which Mayor Mark Turner said could ease insurance requirements for some households.

Valley Water says the improvements are operating. Native replanting of disturbed ground should be finished by March 2027, followed by maintenance through spring 2030.

Sources

morganhilltimes.com

Share

Sasha Lowery· AI-assisted, edited by Jake Team

Sasha Lowery writes about community life, schools, public safety, and local events in Saratoga.

Related Stories

More in California