VTA says BART's San Jose extension is running past its $12.7 billion budget and floats building it in phases

Transit officials told a VTA board committee Thursday that the four-station BART Silicon Valley project will not meet its budget target, with an updated estimate due to the full board in December.

Sasha Lowery· AI-assisted, edited by Jake Team

November 15, 20262 min read

San Jose transit blueprint - illustration, Jake Team LLC

The Santa Clara Valley Transportation Authority has acknowledged that BART's planned extension through downtown San Jose is not on track to stay within its $12.7 billion budget, San José Spotlight reported Friday.

VTA staff delivered the news at a Thursday meeting of a board committee. Tom Maguire, the agency's chief megaprojects officer, said it was too soon for a new cost estimate and that more detail would go to the full VTA board in December, according to the Spotlight. "The project is facing challenging budget pressures, but we're also confident," Maguire said, as quoted by the outlet.

The 5-mile, four-station line has grown far beyond early projections. A 2014 plan estimated $4.7 billion and an opening this year; all four stations are now scheduled to be running by 2037.

What is driving costs

VTA officials pointed to rising construction prices nationwide, federal tariffs, competition for workers and materials from data center construction and higher energy costs, the Spotlight reported. Separately, the agency has spent about a year and a half trying to close a gap of roughly $700 million left when a federal transit grant came in lower than expected.

The federal grant process is not finished, and VTA has said a balanced budget is key to its application.

Tunneling is still planned to start in early 2028. The launch structure for the tunnel boring machine is complete, and every option under study keeps the single large-bore tunnel.

Options and objections

Officials raised the idea of a phased build, opening some stations first and adding others later, though no specific plan has been presented. Some board members suggested cheaper approaches such as light rail, possibly as a stopgap. San Jose Mayor Matt Mahan, a VTA board member, told the Spotlight he still wants all four stations eventually but that phasing may now make the most sense.

Santa Clara Councilmember Suds Jain, also on the VTA board, questioned the timing, telling the Spotlight that the agency knew about the problem but left the board "in the dark."

Sources

sanjosespotlight.com

Share

Sasha Lowery· AI-assisted, edited by Jake Team

Sasha Lowery writes about community life, schools, public safety, and local events in Saratoga.

Related Stories

More in California